Performance of Articulated Concrete Block on Steep Slopes Following Extreme Storm Events
Cellular articulated concrete block (ACB) systems are flexible concrete revetments used to resist the erosive forces of flowing water resulting from elevated velocities and wave action in concentrated flow areas. A typical ACB revetment mat is formed by interlocking precast concrete blocks placed on a geotextile fabric. The interlocking matrix allows versatile structure design for use over varying land contours and grades. ACBs traverse changes in terrain without disrupting the placement patterns and interlocking features of the system, allowing for partial settlement of the underlying foundation without disrupting the integrity of the installation.
Interlocking ACB matrixThe blocks within the (mat) matrix are dense and durable, and the resulting revetment is flexible and porous (Abt 2001). Voids between blocks allow vegetation to establish over time, decreasing flow velocities and improving final appearance. ACBs became part of the erosion protection arsenal within the past 15 years. In 1999, a hydraulic testing protocol was developed to ensure that each block system will satisfy users’ design needs for stream and river stabilization (Leech 1999). Results of testing these protocols have been published (Abt 2001).This article describes the performance of an ACB system under rugged conditions, steep slopes, and exposure to intense rainfall. The site is the Richmond Hill Mine, located in the Black Hills of South Dakota. The mine is part of reclamation efforts undertaken by Lac Minerals LLC. This site was chosen for study because it has several steep downchute channels protected by ACB, and because several storm events equal to or larger than the design storm event have occurred since downchute construction. The ACB system constructed at this site is Tri-lock produced by American Excelsior Inc. To provide some reference for long-term performance of this relatively new engineering product, the article describes the field performance of the downchutes that have already experienced several extreme storm events, specifically:Localized erosion (causing a ‘bridging’ effect) under block connections and between the geotextile and ground surface; andConcrete cracking and fracturing under extreme weather conditions or during long-term exposure.BackgroundThe Richmond Hill Mine is located in western South Dakota in an area that receives an average of approximately 40 in/yr of precipitation. Golder Associates developed a surface water management plan for the property that included a reclaimed overburden stockpile (ROS). Stormwater runoff is conveyed off the ROS in steep downchute channels armored with Tri-lock.The ROS contains five downchute channels constructed in 1994. Three of these downchutes were inspected by the authors in 2001. Downchutes 1 and 2 are located on the south-facing slope, intercepting runoff from vegetated bench channels at regular intervals. Downchute 3 is on the northwest-facing slope. Specific downchute design parameters are outlined in Table 1.
Downchute channel protected by ACBA four-person inspection team consisting of one representative of site management and the authors of this article performed a site investigation, including a detailed inspection of the downchute areas. Notable features included blocks displaying stress cracks after installation. The inspection team performed tests (with a metal probe) between the lock-and-key blocks to determine the presence of voids below the blocks approximately every 10 feet along the downchute length. Overburden Stockpile Downchute ChannelsBeginning on the overburden stockpile, the inspection team examined the downchute channels from the uppermost bench location (initiation point of the ACB portion of the downchute). The downchutes investigated in October 2001 were installed in 1994. The upstream end of the Tri-lock mat was not anchored, but the sides of the downchute mat were anchored into the overburden stockpile cover material. Investigations focused on the blocks in the downchute bed. Site personnel noted that the 4-inch blocks were laid directly onto the geotextile and the open space between blocks backfilled with topsoil. Visual inspection indicated a good vegetative cover including 12-inch-high grasses in the downchute bed. In fact, much of the Tri-lock mat was obscured due to the dense cover.
Paul Clopper, P.E., is manager of Water Resources for Ayres Associates in Fort Collins, CO.