Most of the newer developments had stormwater detention ponds that had been designed and constructed in accordance with standard practices required by Fulton County. There were no detention facilities or stormwater best management practices (BMPs) to control runoff from roadways that were built or widened to meet the needs of an expanding commercial development. Because of these changing conditions in the watershed, the RNCA board decided to focus on a study point at the lower pond, where the impacts were most obvious.MethodsTo determine the cause of flooding, a reconnaissance of the watershed was conducted by walking the streams and dry-weather channels, reviewing United States Geological Survey 7.5-quadrangle maps, reviewing development site plans, and observing rain events in the field. The initial watershed assessment did not identify any single specific condition, facility, or structure upstream that contributed to the flooding in the lower pond. Because no “culprit” structure was found, the problem was identifying the source of flooding and recommending the appropriate action to resolve the problem. Because detention facilities had been built in accordance with ordinances requiring a reduction of runoff to predeveloped rates and were certified by a number of engineers, the problem of initiating a solution to the flooding was difficult for RNCA. Clearly the runoff rates experienced in the neighborhood exceeded the predeveloped rate of stormwater runoff, because significant floods were occurring from rain events producing far less than five-year and 25-year rainfall amounts. RNCA had to answer one particular question: How could this extensive and frequent flooding occur when all new development had facilities to reduce the runoff to predeveloped (natural) rates? To unravel the problem, RNCA decided on a systematic, step-by-step approach to incrementally reduce the flooding and improve water quality. RNCA knew that this approach would take a great deal of commitment and unity among its members because first attempts might not produce noticeable results. Fortunately, this was not the case.The problem of siltation and turbidity was addressed first because it was the most dramatic and obvious. Turbidity was the best representation of the degradation of water quality in the basin and was the most easily resolved by the use of BMPs. Because there was only one new construction project within the boundaries of the watershed at the time of this investigation, the source of the siltation was easily identified. RNCA persistently observed, photographed, and/or videotaped the construction site and notified the Fulton County Department of Environment during every rain event to ensure that compliance was enforced. Resident “watchdogs” inspected the site from an adjacent parking structure and from public streets. Photos were sent to the county to show failed BMPs and the extent of sedimentation leaving the site. Finally, a toll-free hotline was used repeatedly to report these conditions. As a result, Fulton County required the developer and contractor to comply with erosion control standards with aggressive use of BMPs at all times. All exposed soil was covered with a thick layer of mulch, additional silt fences were installed correctly and maintained regularly. Additional BMPs, such as rock check dams, were installed in dry-weather drainage channels, and gravel exit pads were placed at the entrance to the site. Some stormwater was diverted to the other side of the site into a large detention pond that discharged into a neighboring watershed. All this activity greatly reduced the turbidity of runoff flowing to the study point.
Click here for larger viewComparison of the as-built drawing and the inspection photos indicated that a 2-in.-diameter weephole had not been drilled near the bottom of the OCS weir during construction (Figure 3). The weep hole was intended to allow slow, controlled drainage of the vault after rain events. The problem was aggravated by the accumulation of sediment and debris at the weir wall that clogged the 12-in.-diameter hole in the middle of the OCS. The combination of these two factors prevented the vault from detaining any stormwater because water was permanently stored behind the weir. As a result, all the property owners along the dry-weather channel to the study point received full peak flow from this drainage basin during rain events. Several months after the weephole was installed and an additional 12-in.-diameter hole was built into the weir wall of the OCS, a 2.25-in. rain event occurred in the area over a two-hour period without flooding. This was the largest rain event since efforts to control flooding began in July 1999 and demonstrated a remarkable improvement over conditions a year earlier. This amount of rainfall one year earlier would have caused severe overtopping of the streambanks and overflow from the upper pond to the lower pond. ResultsAlthough flooding has been reduced with the modification of the three ponds, this neighborhood has not experienced a five-year to 25-year rain event since completion of large-scale commercial projects upstream. Further modifications might be needed after the watershed has received precipitation from a storm of that magnitude. The upstream area is still the object of intense speculation for further commercial development because a 13.5-ac. tract remains undeveloped, so additional capacity or additional modifications of existing ponds might still be necessary in the future.Results of these actions by RNCA significantly reduced the volume and frequency of flooding and improved water quality in its small watershed. Because such dramatic improvements were made to the flow regime and water quality, wildlife that had been absent has returned. The ponds in the area are no longer choked with sediment and resultant algal blooms. Habitat areas are no longer frequently flooded. Properties along the streambanks are now protected from the ravages of flooding and siltation, and homeowners no longer panic during rain events.ConclusionsThe actions taken by RNCA can serve as a model for other watersheds with similar problems. Adherence to strict land-use rules is not sufficient to maintain water-quality standards within suburban watersheds. Land use must include the aggressive use of a variety of erosion control and water-quality BMPs and a more conservative approach to estimating the predeveloped flow rates in the stormwater design and permitting process. Runoff coefficients used to estimate predeveloped flow rates are too high and result in inadequate storage capacity of detention ponds. In addition, improved stormwater management facilities are not sufficient to control runoff if they are not effectively maintained. By implementing this program, RNCA was able to improve water quality and reduce flooding at minimal cost and with no disruption to the natural watershed. The unintended benefit was a restored wildlife habitat, which is an improvement to the quality of life affecting every homeowner association.